This is to inform that incessant rain and high discharge at one of the under-construction project of the Company i.e. Subansiri Lower HE Project (2 000 MW) has resulted in partial flooding of Power House on 25.09.2022 and all requisite possible measures have been/are being taken to protect the structure and minimize any potential consequential losses. No significant impact is anticipated in project commissioning schedule due to this unforeseen incident except some time for dewatering and cleaning works. This is submitted for information of stakeholders and to address misinformation if any.